Week 27

NEW BUILD 022

Started
July 2007

Overhead frame work complete ready for monitors Good progress in galley-mess deck Units near completion
Oak trims and cupboards complete in accommodation Deck washing system under construction
Main exhaust now being fitted in engine room
 