Harmoni working at sea showing dredges and conveyor
A
steel hulled Scalloper having double chine, transom stern, bulbous bow,
soft nosed stem and rigged for Queenie and Clam fishing with 8 dredges
per side and automated catch handling.
Building fishroom in fabrication shed
Balast fitted in box beam ready for welding up
Good progress on fish room in fabrication shed
Fabrication of bulbous nose
Fish room comes out of fabrication shed ready for lifting into position
Crane takes up the 8.5 ton strain of the fish room
Plating is now well under way
After Christmas holidays work is now in full swing
Jim & Steve fitting bulwarks
Fabrication of deck housing in shed
Deck housing leaves fabrication shed
Birds eye view
Jim checking accuracy
Stearing gear fitted
Below
deck to be subdivided by four watertight bulkheads into :- Aft
accommodation with steering gear, Engine room, Hold and Forepeak
tank/gear store.
Auxiliary engine
Gearbox.
Main engine arrives its a 3406 Caterpillar
Jim&Steve negotiate Cat through aperture with a tight squeeze
Welding plant comes aboard for repair & maintenance work at sea
Aluminium for shelter deck arrives and laid out ready for welding
Automated emptying door comes on board
Emptying doors in place with queenie riddles
Main
deck is to have an aft deckhouse for galley and mess with an Aluminum
wheelhouse fitted over. Forward trawl winch, hinged outriggers, lifting
gantry and Queenie riddles.
Prop shaft fitted
Hydraulic rams in place for lifting scallop emptying hoppers
Internal view of scallop riddles with conveyer belt just in view
Dredge lifting gallows and
forward mast fitted also showing opening to conveyor belt
Navigation & electronics being fitted to masts by Robbins marine electronics of Liverpool
Harmani gets her name on stern & Tony fitting charm bars
Covers removed from Harmoni and first coat of two pack primer now on
Hydrolic oil tank and service diesel tank fitted in engine room
Ice making plant installed in fish room
Starboard side galley area
Removable panel for access to steering gear in accommodation block
Urethane&coating systems setting up for insulation injecting
Shower tiled out in Harmoni
A
full length Aluminum alloy shelter deck is to be fitted over the main
deck. The shelter deck is to incorporate troughs, set into the deck at
side over the length of the dredge bars to receive the catch.